Long Delays Caused by Construction Has Some Drivers Willing to Pay Out-of-Pocket to Get It Done Sooner - NBC 5 Dallas-Fort Worth

Long Delays Caused by Construction Has Some Drivers Willing to Pay Out-of-Pocket to Get It Done Sooner

    processing...

    NEWSLETTERS

    Construction Delays Have Some Drivers Offering to Pay

    Some people have suggested on social media that motorists should take up a collection for a bonus fund to offer the contractor if a construction job on Interstate 20 in Weatherford job gets completed before Easter or summer 2020. (Published Wednesday, Nov. 13, 2019)

    Traffic tie-ups are the norm in front of David's Stove Shop on Mikus Road and Interstate 20 caused by construction in Weatherford. The shop owner said it's been going about a couple of years, but it feels like it's been much longer.

    "Feels like 10 years," shop owner David Clack said.

    It also seems like an eternity for drivers sitting in the traffic trying to get through the intersections.

    "Very slow," driver Doug Walker said. "I get tired of having to sit at the light."

    Shooting at 2nd Wisconsin High School Leaves Community in Shock

    [NATL] Shooting at 2nd Wisconsin High School Leaves Community in Shock

    A school officer and a student were injured at Wisoonsin's Oshkosh West High School Tuesday morning, when the student was shot after attempting to stab the office with a sharp object. The shooting comes just one day after a school resource officer at Waukesha South High School shot a 17-year-old armed student who refused to drop his weapon.

    (Published Wednesday, Dec. 4, 2019)

    During the evening rush hour, traffic backed up exiting I-20. There's one lane with a long line of cars waiting in a single file line to make their turn.

    "It's about a 5 to 8 minute wait at the light to get through every day," driver Jennifer Covarrubias said. "It's frustrating, but I don't know what else you are going to do. There is no other way around it."

    "It takes two cycles sometimes because traffic is backed up towards the lake," Clack said. "Gosh, I never counted the cars, but I bet there is 40 to 50 in line."

    A Texas Department of Transportation spokesperson said the project is a part of a larger, long-term effort to manage increasing volumes. However, it did encounter delays with water seepage and stability issues associated with a retaining wall construction. There were also grading issues due to old concrete paving discovered from 1940.

    Some people have suggested on social media that motorists should take up a collection for a bonus fund to offer the contractor if the job gets completed before Easter or summer 2020.

    Some drivers like that idea.

    Key Findings of Fact from 'The Trump-Ukraine Impeachment Inquiry Report'

    [NATL] Key Findings of Fact from 'The Trump-Ukraine Impeachment Inquiry Report'

    The House Intelligence Committee released a report outlining evidence for the impeachment of President Donald Trump.

    (Published Wednesday, Dec. 4, 2019)

    "Absolutely yes," Covarrubias said. "I would absolutely pay for that."

    "I am chipping in my taxes," Walker said.

    TxDOT said asphalt paving is set to begin this month, weather permitting. The estimated completion is 2020.