Toll Lanes Planned for LBJ Between US 75 and I-30 - NBC 5 Dallas-Fort Worth

Toll Lanes Planned for LBJ Between US 75 and I-30

Ten-year project would expand I-635, cost nearly $2 billion

    processing...

    NEWSLETTERS

    Toll Lanes Planned for LBJ Between US 75 and I-30

    A plan to expand a nearly 11-mile stretch of Interstate 635 between the interchanges with US 75 Central Expressway and Interstate 30 would include the installation of managed toll lanes for the entirety of the route. (Published Monday, Nov. 6, 2017)

    A plan to expand a nearly 11-mile stretch of Interstate 635 between the interchanges with US 75 Central Expressway and Interstate 30 would include the installation of managed toll lanes for the entirety of the route.

    The North Central Texas Council of Governments and the Texas Department of Transportation have long planned an expansion of LBJ Freeway east of the High Five interchange. Managed toll lanes had previously been planned for only a portion of the project.

    The finished project, if it is completed as planned, would include five free lanes in each direction, two managed toll lanes in each direction, as well as continuous frontage roads for the entire stretch.

    The LBJ expansion would take an estimated ten years to complete, and the work would be done in stages:

    Man Takes Dog With Terminal Cancer on Ultimate Road Trip

    [DFW] Man Takes Dog With Terminal Cancer on Ultimate Road Trip

    Attleboro, Massachusetts Mayor Paul Heroux is devoted to his dog, Mura. When he found out she has just months to live, he took her on one last trip to make sure they made the most of their last weeks together.

    (Published Tuesday, Nov. 13, 2018)

    • The section between US 75 and Royal Lane/Miller Road would be built from 2019 to 2022.

    • The section from Royal Lane/Miller Road to near State Highway 78 (Garland Road) would be built from 2021-2023.

    • The section from Garland Road to Interstate 30 would be built from 2023 to 2026.

    • The Interstate 30 interchange would be rebuilt from 2025 to 2027.

    The estimated price tag for the project would be approximately $1.8 billion.