2nd Texas-Oklahoma 345-Kilovolt Project Done

Utility crews have finished a second 345-kilovolt transmission line between the Texas Panhandle and Oklahoma to provide more export capacity for wind-generated power.

Xcel Energy in Amarillo on Monday announced completion of the estimated 200-mile line from near Abernathy, Texas, to Woodward, Oklahoma. It's part of a $64 million partnership with Oklahoma Gas and Electric Company.

Xcel Energy says the Texas stretch was energized last week when a connection was made to the Oklahoma segment completed by OG&E.

Xcel Energy on May 22 announced completion of the first 345-kilovolt line in the agreement. That 130-mile line runs between Hitchland, Texas, and Woodward.
 

Copyright AP - Associated Press